Hi
It is a machine used for textile application.
Machine needs 2400 sensors to monitor each positions.
One set of pcbs (1master, 2 slave) needed for 24 position.
V have a 24v 10amps SMPD line runs throughout machine.
Each 24 positions will be supplied with 24v line tapped from the bus.
V convert it to 5v and 3.3v for controller and other operations.
As v plan to have source as 10amps or max at 20amps, v need to manage supply without loading with more current consumption for SMPS.
So v believe switching method supply at a time 4 per 24 positions can be done.
So that in each 24 nos out of 2400 positions, v can make a control by switching on 4 positions at a time for few millisecond and then next 4 or few millisecond ...like wise for 24 position 6 times can b switched in one cycle.
Then repeating d same process.
If v hv a design for one set of 24 positions, v can repeat for entire machine for each 24positions.
Hope i hav detailed and will be helpful.